RRD Imaging
Carseldine
design + construct
13 weeks
470m²
KEY ELEMENTS
Early Contractor Involvement allowed the project to be de-risked, and design to be developed in line with the agreed project budget
Full turnkey delivery for our client including loose furniture, whitegoods and signage
Lead hielding installation and certification + detailed services integration + coordination for radiology equipment
Coordination of RF cage installation and integration of associated finishes and services
Underslab hydraulic drainage completed within an active base build site ahead of fitout commencing
Shopfront modifications to suit the new layout
Imaging equipment delivery to the Level 1 tenancy through the glazed façade
Cranage of mechanical condenser units to the roof within a live precinct
Close coordination with the landlord throughout approvals and construction

ABOUT THE PROJECT
BELNIC was engaged to design and construct RRD Imaging’s new radiology practice at Carseldine.
Working with the client, an agreed construction budget was established early, allowing the design to be developed around the project requirements and budget before progressing into construction.
The 470m² first-floor practice incorporates MRI, CT, X-ray/OPG, mammography, BMD and four ultrasound rooms, supported by recovery, change and sub-waiting areas, reporting, administration and staff facilities.
Delivered over a 13-week programme within an active base build, the project required detailed coordination between the building works, specialist radiology requirements, equipment vendors and landlord.
Equipment access and installation also played a key role in the construction sequencing, particularly with the practice located on Level 1.