design + construct

13 weeks

470m²

KEY ELEMENTS

  • Early Contractor Involvement allowed the project to be de-risked, and design to be developed in line with the agreed project budget

  • Full turnkey delivery for our client including loose furniture, whitegoods and signage

  • Lead hielding installation and certification + detailed services integration + coordination for radiology equipment

  • Coordination of RF cage installation and integration of associated finishes and services

  • Underslab hydraulic drainage completed within an active base build site ahead of fitout commencing

  • Shopfront modifications to suit the new layout

  • Imaging equipment delivery to the Level 1 tenancy through the glazed façade

  • Cranage of mechanical condenser units to the roof within a live precinct

  • Close coordination with the landlord throughout approvals and construction

RRD Imaging
RRD Imaging

​ABOUT THE PROJECT​

BELNIC was engaged to design and construct RRD Imaging’s new radiology practice at Carseldine.
Working with the client, an agreed construction budget was established early, allowing the design to be developed around the project requirements and budget before progressing into construction.

The 470m² first-floor practice incorporates MRI, CT, X-ray/OPG, mammography, BMD and four ultrasound rooms, supported by recovery, change and sub-waiting areas, reporting, administration and staff facilities.

Delivered over a 13-week programme within an active base build, the project required detailed coordination between the building works, specialist radiology requirements, equipment vendors and landlord.

Equipment access and installation also played a key role in the construction sequencing, particularly with the practice located on Level 1.